Week 17
Monday, February 26: We started the day fitting the eave drip edge. It was fitted in two pieces with an 8" long piece added under the butt joint about 2/3 of the way down the building. The special cove cut shown previously was made in each end to accept the rake end drip edge. Monday, February 26: This picture shows the fit between the rake end drip edge (left) and the eave drip edge (right). Monday, February 26: After the drip edge was installed we snapped a chalk line and then installed the starter course of shingles. The starter course was cut from tabbed shingles in such a manner as to remove the tabbed section. By doing this the starter course had no slots, insuring that there would be shingle material under the end seams of the next course. Also placing adhesive along lower edge to seal to bottom edge of first shingle - reduce risk of wind getting under first course) Monday February 26...