Week 17

Image
Monday, February 26:  We started the day fitting the eave drip edge.  It was fitted in two pieces with an 8" long piece added under the butt joint about 2/3 of the way down the building.  The special cove cut shown previously was made in each end to accept the rake end drip edge.  Monday, February 26:  This picture shows the fit between the rake end drip edge (left) and the eave drip edge (right). Monday, February 26:  After the drip edge was installed we snapped a chalk line and then installed the starter course of shingles.  The starter course was cut from tabbed shingles in such a manner as to remove the tabbed section.  By doing this the starter course had no slots, insuring that there would be shingle material under the end seams of the next course.   Also placing adhesive along lower edge to seal to bottom edge of first shingle - reduce risk of wind getting under first course) Monday February 26...

Week 18

Image
Monday, March 5:  We started the the day with Comp Testing in the shop. Monday, March 5:  We caulked the shed wall corner seams using acrylic latex caulk.  Then we applied Typar building wrap, which blocks water and air from entering the building while allowing moisture to move out of the building.  (good!) Monday, March 5:  The first course of wrap has been applied.  It is secured with cap staples that incorporate plastic washers.  We will work from the bottom up, to allow top over bottom overlaps. Wednesday, March 7:  Started the day with Comp Test computer exercises. Wednesday, March 7:  We completed application of building wrap.  Orange cap staples are visible. Vertical and horizontal seams were overlapped and then tapped.   Wednesday, March 7:  This picture shows the fit under the rake.  We used our rafter template to layout the cut lines on the building wrap. ...

Week 16

Image
Monday, February 19:  President's Day.  No Class. Wednesday, February 21:  We cut and attached the eave fascia board today.  It was fastened such that it extended 3/8" below the soffit board for it's entire length, so that rainwater will drip off the fascia rather than wetting the soffit.  Small shims were added to several rafter ends keeping the fascia board straight over it's length.  It was fastened to the rafter ends using 7d galvanized box nails. Wednesday, February 21:  The rake fascia boards were carefully cut flush to the eve fascia using a hand saw Wednesday, February 21:  The next step was to install the rake soffit boards.  The boards were rough cut to length and then one edge was straightened on the jointer to allow a tight fight against the fascia. Then the first board (in this picture, the board on the right) was square cut to length and pinned into place.  Next, the second board was fitt...

Week 15

Image
Monday, February 12:  We used a circular saw to trim the roof decking flush with the outside of the gable ladder, on both ends of the building.  The saw blade was set to the depth of the roof decking to avoid marking the rake end fascia board. Monday, February 12:  After snapping lines across the tails of the rafters to mark the soffit cut line, and the top of the lookout, and installing a scrap sheathing piece to act as a temporary ledger for the lookouts, the rafter tail soffit cuts are made.   Monday, February 12:  Here is a good view of one of the lookouts.  The lookout has been carefully leveled so that the soffit board will lay flat along it's entire length.  The next step will be to snap a chalk line along the bottom of the lookouts to allow the soffit board to be nailed on straight.  The outer soffit will be nailed first, then the vent and inner soffit will be added.  The string line shown here was used ...