Week 25
Monday, April 30: We started the day with in-shop Comp Testing, which included a wall layout, story pole layout, hip rafter layout, and a string line plumb bob exercise. Monday, April 30: The lower door lock has been installed on the Zip System shed door, such that 3/16 inch clearance is maintained over the sill plate when unlocked, and the lock engages through the plate by about 3/8" when locked. Monday, April 30: A small "strike plate" was cut from aluminum angle stock and drilled to accept mounting screws and the lock bolt. It was then mounted to the Azek head jamb. Monday, April 30: We removed the metal eave fascia pieces and installed additional pieces at the corner to close the corner openings where the bottom edge of the fascia meets the bottom edge of the return. We then cut, bent and installed new eave fascia pieces. The result is more attractive and more water tight. Wednesday, May 2: We started th...