Week 6
Monday, November 7: Here, an elevation is being read at each corner of the shed floor using a tape measure and laser. Using the readings the floor will be leveled with shims. This will allow the walls to be erected plum to the shed floor. Shims were also installed under the centers of the outside skids to prevent "bowing".
Monday, November 7: This is the beginning of the shed back wall. Plates and studs are 2 x4, with studs mounted on 16" centers. The interior studs are fastened to the plates, top and bottom, using 2 each 16d common nails. Nails are driven through the plates and into the stud ends.
Monday, November 7: This is a fastening detail picture taken at the corner of the wall. The corner post is made up of two 2 x 4's, oriented at 90 degrees. The plates are fastened to the corner posts, at top and bottom using three, 3" screws. The plates were predrilled to prevent splitting, and also to prevent the plate from being forced away from the post as the threads engaged.
Monday, November 7: The wall framing is nearing completion. A second top plate will be added, shortened at each end by 3 1/2" to allow overlap with the adjoining walls. The framing will then be checked for square and temporarily toe nailed to the floor to maintain squareness. OSB sheathing will then be added, fastened with 8d nails.
Monday, November 7: The first wall, which will be the shed back wall has been erected and braced. The wall has been braced at slightly greater than 90 degrees to the floor which will make raising of end walls easier. The wall will be brought in to alignment with the floor chalk line and then nailed in place using two 16d common nails at each stud location. Final plumbing of the wall will be done after the other walls are raised.
Wednesday, November 8: The camera is looking down at the bottom plate of the back wall. The back wall is fastened to the floor using two 16d common nails at each stud. The nail on the left has been driven at an angle through the bottom plate and into the floor joist that is just under this stud. A second nail has been driven though the bottom plate and into the rim joist. The temporary "toe nails" have been removed.
Wednesday, November 8: Building of front wall begins. Plates, studs, jacks, cripples and headers have been cut to length.
Wednesday, November 8: In order to improve access for nailing, the window and door assemblies are built first. Here are the two window assemblies. Bottom cripple studs are visible in the foreground. The plates and corner posts have been built and are partially visible to the right on the shed floor.
Wednesday, November 8: A detail shot of a window header. The header is built of two pieces of 2 x 6 lumber, joined with 16d nails driven at an angle. The header rests on the jack stud and is secured to the king stud by through nailing with four 16d nails on each end. Cripple studs will be added above the header when the window assembly is added to the wall. This arrangement will allow the load from above the window to be transferred to the jack and king studs
Wednesday, November 8: Here is a better view of the front wall top and bottom plates and the corner posts. In the foreground from left to right are two door king studs of man-made material, two standard 2-4 jack studs, a door header of man made-material, and a number of lengths of 2 x 4 stock. On Friday there will be no class, so on Monday we will build the door opening and then finish building the front wall.