Week 9
Monday, November 27: A short day for me. Work started with the plumbing of one end and two side walls using plumb bob and checking with a level. Walls were then braced to hold plumb while second top plate was added to this end wall. The second top plate was spliced near midpoint, with seam centered on a stud as per code. Fasting was done at corner posts using three inch star drive screws. Plate to plate fastening was done with 16d common nails driven at an angle for strength and to hide nail points. After I left, my team mates snapped a line across the end wall studs to mark location of sheathing. OSB sheathing was then added and secured using 8d nails.
Monday, November 27: When I returned late in the afternoon my work mates had also finished cutting out parts for the end wall, which will incorporate a large door. The king studs are of man made laminated strand lumber material and are straight and free of defects. The jack studs, if nailed properly, can be held straight by the king studs. The door header is fabricated using two 2 x4's. The first top plate is visible to the rear and the bottom plate is visible in the foreground.
Monday, November 27: A common rafter practice exercise. The rafter dimensions were calculated using given information, and a rafter was laid out on the 1 x 6 shown in this picture. During this exercise I learned a better technique for setting up and aligning a framing square to prevent "reversing" the slope.
Wednesday, November 29: We cut the sheathing out of the front wall of the shed using a sawzall, working from the inside of the shed. A plunge cut technique was used to start each cut.
Wednesday, November 29: We assembled and raised the end wall, which will have a large door. The door was plumbed using a six-foot level. The upper length of the double top plate was spliced over the door header. Sheathing was added after the door went up.
Wednesday, November 29: This photo shows the sheathing on the end wall. Because this will be the gable end the sheathing has been brought up to cover only have of the lower length of the double top plate.
Wednesday, November 29: This detail photo was taken from the inside of the end wall we just raised. The door header, LSL king stud and, 2 x 4 jack stud, and double top plates are visible.
Friday, December 1: All four walls are up, and it is time to start on the roof. The first step was to check the vertical dimensions of the shed, which will allow us to begin to calculate the roof slope that will give us an overall height of 10' 6".
Friday, December 1: The vertical dimensions of the skid, floor system, top and bottom plates and studs have been laid out on a story board, illustrated above.
Friday, December 1: Here the walls are being checked for straightness at the top. Strings are stretched from 1 1/2" thick blocks and measurements from the string to the top plate are taken along both walls.