Monday, January 22, 2018:  We started the day with the eighth round of classroom comp testing, followed by some classroom time and two rafter exercises in the shop.  Then we set up the cut station shown above.  The 2 x 4's (badly twisted) are sacrificial supports that let us support the material on both sides of the cut when cutting sheet goods.




Monday, January 22:  Another sheet of Advantech roof decking has been applied.  Fasteners are 8d common nails.  Decking on this side is oriented with the tongue up.  The other side will be reversed. This will allow us to cut all of the remaining material needed from a single sheet, and use the tongue and groove interlock on all but the small end pieces. Those pieces will be secured using clips.




Monday, January 22:  A shelf has been added for finish lumber and drip edge.  Roof shingles have been stockpiled.  Soon we will put braces across the top of the walls from side to side, and then remove the temporary wall braces shown here.




Wednesday, January 24:  An inventory list for each shed was developed in the classroom, and will live in the shed in this plastic folder.  Notes regarding location and processing of material are included.




Wednesday, January 24:  Another lift of scaffolding was added to facilitate roof decking installation.




Wednesday, January 24:  Rood decking visible on both sides.  Tops at  ridge / gable ends remain to be done.




Friday, January 27:  The last decking piece has been added to the right side.  It is nailed to the last two rafters and secured to the decking course below with clips.  The opening for the ridge vent is visible.





Friday, January 27:  Roof deck is closed in except for opening for installation of ridge vent.


Friday, January 27:  We selected material for our rake end ladders from this rough lumber stickered wood pile in the shop.




Friday, January 27:  This lumber has been brushed clean and rough cut to length for the rake end ladder long members.  Next week we will remove knots, plane flat, joint one edge,  and rip to 3 1/2" width.  We will then be ready to begin building the rake end ladders.