Posts

Week 11

Image
Monday, December 11:  We started the day with another round of comp testing in the shop.  This wall mock up allows us to check the end studs for plumb, both front to back and side to side, using a plumb bob.   It also allows us to check the top plate for straightness using a string line mounted on gauge blocks.  The days' testing also included paper lay-outs, rafter questions, and wood characteristics questions. Monday, December 11:  End rafters are installed.  Care was taken to select straight stock for the end, or rake, rafters.  A temporary support post under the ridge board is shown.  This will be removed prior to installation of the gable end studs. Monday, December 11:  The end rafters and ridge board at the other end of the shed are shown here. A shim has been placed between the temporary supporting post and the ridge board to raise it slightly for a good fit between the rafters and the ridge board. ...

Week 10

Image
Monday, December 4:  We started the day by straightening the upper top plate on the shed back wall. We removed the existing plate, cut it, and set the bowed portion aside.  We then spliced in straight material, with the splice directly over a stud. Monday, December 4:  It is difficult to see, but we laid out lines on the outside of the shed back wall to model roof rafters.  A straight baseline the width of the building was snapped with a chalkline, and then we snapped a perpendicular line at the midpoint.  The wooden block shown here represents the ridge board. Monday, December 4:  We ran calculations which allowed us to lay out and begin cutting rafter templates using 1x6 pine boards.  These calculations also allowed us to snap the layout lines on the back of the shed wall. Monday, December 4:  Here is a close up of the birds mouth, which will let the rafter sit on the top of the wall framing an...

Week 9

Image
Monday, November 27:  A short day for me.  Work started with the plumbing of one end and two side walls using plumb bob and checking with a level.  Walls were then braced to hold plumb while second top plate was added to this end wall.  The second top plate was spliced near midpoint, with seam centered on a stud as per code.  Fasting was done at corner posts using three inch star drive screws.  Plate to plate fastening was done with 16d common nails driven at an angle for strength and to hide nail points.  After I left, my team mates snapped a line across the end wall studs to mark location of sheathing.  OSB sheathing was then added and secured using 8d nails. Monday, November 27:  When I returned late in the afternoon my work mates had also finished cutting out parts for the end wall, which will incorporate a large door.  The king studs are of man made laminated strand lumber material and are straight and free of def...

Week 8

Image
Monday, November 20:  A rafter layout exercise.  The process begins with a series of calculations in which the total run (which can be expressed as units of run), the unit length, the line length, overhang and overall length are determined.  Other information, including the roof slope are given.  The framing square can be set to the roof slope using small gauges that are attached to the appropriate points on the square.  Then the square can be used to accurately lay out both the plum and vertical lines needed to cut out the rafter.  On the jobsight, this layout would be done on two pieces of stock, the better of which would be used as a template to trace out the other rafters. Monday, November 20:  Today we built and raised the end wall.  Sheathing will not be added until we plumb and secure the walls. Monday, November 20:  This picture shows the bottom plate of the front wall.  Two 16d common nails have...

Week 7

Image
Monday, November 13:  We started the day with shop comp test exercises.  This picture shows a wall frame mock up.  Student's are asked determine how far from straight the top plate is, and how far from plum (both front to back and side to side) the end studs are.  This is done by taking string to framing measurements.  A plumb bob is visible in the foreground. Monday, November 13:  Assembly of the shed front wall.  Left - The door rough opening framework consisting of two LSL king studs, 2 x 4 jack studs and LSL header.  Right - The rough opening framework for one of two windows.  Cripples, top and bottom, and headers are in place.  Three inch screws were used to fastens LSL components, 16d common nails for other framing.  By sighting along the front wall studs to the back wall, you can see that a front wall stud immediately to the left of the door opening is still missing. Monday, November 13: ...